Key Lake DTMF Tailings Project
Key Lake DTMF Tailings Project
Project Description:
New Tailings Distribution to existing ponds with significant upgrades to existing Tailings Infrastructure.
Scope of work:
- New Cable Tray Installation for Existing Utilidor to accommodate heater installations
- Cable Installation for Heaters, CDP, Dupline System, EHT and Lighting
- New CDP and PLC installations
- Pressure and Flow Instrumentation Installation
- EHT and Control for Tailings Lines